on 02-11-2012 5:46 PM
Bonjour,
In my RTCTOOL report, I have written as a warning:
7. Note 12103 Collectors and TCOLL
Description Planning table TCOLL for SAP workload collectors for 700 (note 966309 )
Implementation Press the lights icon to get the detailed check log.
Add missing entries to table TCOLL using ST03N > Expert Mode > Collector
and Performance DB > Performance Monitor Collector > Execution Times.
Schedule RSCOLL00 as an hourly batch job if not scheduled.
Everything is green , but: RSSTAT98 has System A instead of S -> is in yellow.
If I go to st03n - Performance Monitor Collecto - Execution times + Table maintenance, I do not have any valid report: RSCOLL00
Any ideas on how to get green ?
Thanks
I suggest you should check for the note and the probelm.
Basis Release 6.40: Note 970449 describes the contents of table TCOLL
for Release 6.40.
Basis Release 7.00: Note 966309 describes the contents of table TCOLL
for Release 7.00.
Basis Release 7.10: Note 966631 describes the contents of table TCOLL
for Release 7.10.
Alos check the job logs of SAP_COLLECTOR_FOR_PERFMONITOR.
But if you want to just make it green then you can do so :
Click on the problem line then click F6 or Set-->Green button on the top.
Regards
Rajan Arora
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.