non working days in Deployment

Former Member
0 Kudos

Hi all

When running the deployment, system is proposing a non working date in the deployment order although a shipping calendar is assign to the location.

Saturdays and Sundays are non working days in the shipping calendar.

Does anybody knows how to fix this issue?

thanks so much

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member187488
Active Contributor
0 Kudos

Hello,

The problem should not be with deployment.

Deployment only "confirms" the planned distribution demands created by heuristic (or other planning run).

You must first make sure that there's no distribution demands created in non-working days by the planning run before deployment.

Please make sure that you have set the calendars correctly and run the planning run again.

Best Regards,

Ada

Former Member
0 Kudos

Pls check the below......

1. Check the Shipping and Reciving Calender in /n/sapapo/LOC3

2. check the Time Stream ID and the attched Calender and Time Zone.For Test generate the Periods through calculation rule once again

Regards,

Rajesh Patil