Dear All,
I have to define summer and midterm holidays to factory calendar. I defined them by using "special rules" in transaction SCAL. I saw the days as holiday in factory calendar. On the other hand, when I use function HR_RO_WORKDAYS_IN_INTERVAL to read workdays in a period, the function reads that holiday days as workdays. How can I read that days as holiday?
May I define holiday periods by using "special rules" in factory calendar?
Thanks
Hi Arjuna,
Map your Holiday calendar to factory calendar and assign that factory calendar to program of study.
Regards
Vinod Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Arjuna,
I will suggest you to control Class period time limit "0200" rather than factory. Event planning will take care rest of the issues automatically. It will reserve the resources between "0200" time interval. If I am understanding your issue correctly. You want to control classes not HR calendar.
Best Regards,
Prabhat Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.