on 02-09-2012 10:35 AM
Hello Guys
How to replicate a PO from SRM to SRM SUS Client in case of PO created in SRM SUS scenario.
Any configuration and back ground job needs to be scheduled. Also for the corresponding documents from SRM to SUS and Vice versa.
Second, why middle ware PI is used for replication of vendors from SRM to SRM SUS as they both deploy on same system with different client.
Please reply guys
Thanks.
Edited by: santhosh.s on Feb 13, 2012 8:53 AM
Edited by: santhosh.s on Feb 13, 2012 8:53 AM
Edited by: santhosh.s on Feb 13, 2012 8:57 AM
Any idea, please reply guys
Edited by: santhosh.s on Feb 23, 2012 3:42 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Santosh,
As you are using extended classic scenario for transferring PO from SRM EBP to SRM SUS.
You can schedule a report RSPPFPROCESS for every minute with following varient
Application - BBP_PD
Action Profile - BBP_PD_PO
Action Defination - STANDARD_PO
Promotion Status - (0) Not Processed
and also select Processing withhout dialog checkbox.
Regards,
Pawan Keshwani