activating WCM for control key WCM (operation level)

Former Member
0 Kudos

Hi Guys,

I want to activate WCM in the PM order when i enter WCM control key in operations.

I do NOT want to activate it using "Activate Work Clearance Management for Maintenance Orders".

I have done all the config but maybe i missed something as the work approval icon is not appearing for WCM key in order.

Can someone think of what i may have missed?

Accepted Solutions (0)

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Have you grouped approvals in an approval group?

Former Member
0 Kudos

I guess it wont solve my problem as the WCM is working at operation level in another system without it

any more suggestions?