Hi,

We are planning to scheduled background user level risk analysis(SAP RAR 5.3) on a weekly basis , and we want the background report(user analysis report) to be sent automatically to the certain business function GRC key user.

Is this acheivable on SAP GRC RAR 5.3? if so, whats the procedure?

Thanks,

Sri

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Sri

I don't think we have any such out of box feature on RAR 5.3. I guess it's not even there in GRC10,

Thanks

Vijay Ch

Former Member
0 Kudos

Hello!!

I'm pretty sure that there's no such functionality in GRC 5.3.

If you want a custom solution, you can work with the spool files that are saved in the location defined as: "Background Job Spool File Location" in RAR.