Hi all,
I have activated BCS and with AVC check. Then I upload the original budget and post some Returns or Transfer in order to change the original budget.
Despite AVC check is activated the system allow me to post a negative budget:
Original budget: 1,000
Returns: 1,001-
Actual budget 1-
It also happen with release budget.
Original budget: 1,000
Released budget: 500
Returns -600
Actual budget 400
Please help,
Thanks in advance,
Max
02-08-2012 3:27 PM
Hi,
It's allowed to post negative budget in BCS. If you want to close this, define consistency check strategy. Check note 983853 for further info.