on 02-07-2012 4:34 PM
I tried to change Resource type in APO from "Multi-mixed" to "Single". After this, I am getting error when I am trying to create planned order in APO. Details are as follows.
Work center in ECC was setup with flag "Can be used by several
operations".When this work center was integrated to APO, resource with
resource category "Multi-mixed" created in APO .
Now, we wanted to change this resource to Resource type"Single". So, we
unchecked the flag "Can be used by several operations" in ECC and
integrated work center and PDS.
Now, when I try to create PP/DS planned orders (Manually as well in
planning run) in product view for materials that use this resource in
APO, I am getting the following error.
Capacity requirement is invalid
Message no. /SAPAPO/OM601
I found an SAP note 924562. This note says resource type changes are
currently not supported in APO. However, it does not say how this error
can be fixed and allow us to create planned orders in system.
Can you please e-mail me steps I should follow to fix this error and be
able to create planned orders?
I had put the flag "Can be used by several operations" back on and
integrated work center and PDS again. This did not help fix the issue.
Thanks for your help.
Srini
Dear Srini,
After setting the flag back, you can delete the blocked queue then run report RIMODINI to transfer the work center and PDS to APO again.
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.