When i am creating planned order in APO, the finish date is showing the desired date as per the demand but the start date is always taking todays date and not scheduling backwards properly, eventhogh my scheduling type is backward with infinite.
Could you please let me know the reason for the same.
Thanks,
Prash
Hi Prash,
It's not possible to plan in the past, so you would not see a start date in the past.
If you would give a demand date in the future, the start date would get calculated backwards. However, it can't go into the past. At the most, you can get a start date for today for any order that is created today.
Thanks - Pawan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pawan,
Kindly note that the issue is not regarding the past date and it is happening for a particular product only.
Here eventhough we are creating an order in the long future,the start date is showing the current date means it is always taking the current date as start date eventhogh it is backward with infinite scheduling.
Thanks,
Prash
Edited by: Prasanth P G on Feb 8, 2012 11:09 AM