on 02-06-2012 4:36 PM
Hi Experts,
We are using WBS Elements in Procurement Process, When we creating PR with account assignment to WBS with Category P
System is checking Budget and availability control is working fine but when i Creating PR against the AA Category Q
System is not checking the Budget Availability Control
Please help to fix this issue.
Regards
BK
Hi Barath,
I believe that your configuration is such that the inventoried materials are not taken under commitment whereas the direct costs/expenses are taken as commitment lines.
All you need is to check if a cost element is create for the G/L that appears while you are creating PR or PO. If no cost element exists, then system will not check with the Budget.
I will give you a simple example to understand this:
Make a PO with acc ass cat "P" and see the account assignment tab. Now see the G/L. Make a note of it. Now enter the WBS in the relevant section and you will find that the G/L has changed. If you check that G/L, a cost element will be assigned to that.
Now again make a PO with acc ass category "Q". See the Account assignment tab. Note down the G/L. Enter the WBS element and you will find that the same G/L appears again. If you analyse that G/L, there will be no cost element created for that.
The G/L basically appears based on the Automatic Account Determination by your MM/FI Consultant against the Relevant Transaction Keys.
Hope it helps you.
Raghav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bharath,
Please ask your CO consultant to create statistical cost element of category 90 for that particular G/L account. Then it'll check budget for account assingnment category Q.
Regards,
Murthy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi bharath,
Please check whether the stock g/l for which material you are raising PR against AA category Q is created as statistical cost element or not. if not create particular stock g/l as statistical cost element, then only System will check Budget and availability control.
Hope it will help, check and revert.
Regards
Srikanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Bharat,
Check in OME9 with Acct. Assignment category Q weather you have maintained project as mandatory entry.
If not ,make the corrections.
regards,
ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.