I am not able to cancel the service contract.

Am getting this message " The next possible cancellation date is 04.05.2013"

how to resolve it?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You need to create a Z cancellation procedure for "CS Cancel from the acceptance date".Ex-Z006 And then use it.By that in the line level contract data tab when you update the cancellation procedure to Z006 and then update the acceptance date to ur desired date for cancellation.Then once you press enter, In the contract overview sceen you can see the Contract End date being updated your desired date of cancellation.

Answers (2)

Answers (2)

jobi_t
Contributor
0 Kudos

I created contrac on 06.02.2012, this valid till 07.02.2012

I want to cancel this today, But I can't

I tried above steps

how to resolve it

jpfriends079
Active Contributor
0 Kudos

For your requirement, the cancellation rule (TCode VOVL) should have following characteristics:

Canc.date

02

Contract Start Date

Notice

1-

Canc.unit

1

Day

Canc.period

1

Period unit

3

Month

Further, I believe you will not be able to see any change in config for the current contract. To test these any new configuration change you might need to create new contract and try.

Regards

JP

jobi_t
Contributor
0 Kudos

AM getting this error,

The next possible cancellation date

is the 07.02.2012. Copy cancelation

date? ( I want to cancel's current date(06.02.2012))

how to add screen shot here, I can add that also

jpfriends079
Active Contributor
0 Kudos

Try with changing the validity to date of contract to 04.02.2012 or 06.02.2012.

Regards

JP

jobi_t
Contributor
0 Kudos

@JP,thanks for ur support

I tried that also.

Next Possible cancellation date is 07.02.2013, after enter button second message is0 "The next possible cancellation date

is the 06.02.2013" Copy cancelation date?

It's not allowing in current date.

There is any setting in Contract Profile?

Jobi

jpfriends079
Active Contributor
0 Kudos

If you are changing existing configuration and trying in existing doc, will not help .

As new changes will not have any effect on existing contract doc.

If you want to try the new config, go for in new contract processing.

Regards

JP

jobi_t
Contributor
0 Kudos

I tried with new docs only. still same

jpfriends079
Active Contributor
0 Kudos

Is your contract profile carries different cancellation rule as suggested by my in previous post?

Regards

JP

jobi_t
Contributor
0 Kudos

Yes it is, 3 rules are coming at the time of cancellation.

jpfriends079
Active Contributor
0 Kudos

For your requirement it should come as 0001 - Cancel. up to 1 wk after contract start.

So, try

Cancellation proced.

0001

Cancl to ValidPrdEnd, yrly withdrwlRight

in your contract profile.

Regards

JP

jobi_t
Contributor
0 Kudos

Cancellat.proc. MAHN Cancell.recvd 06.02.2012 Req canc.date 06.02.2012

Contract end 07.02.2012

Periods of Notice

MAHN MAH Cancel. up to 1 wk after contract st 06.02.2012 07.02.2012 06.02.2012 07.02.2012

I tried with 06.02.2012(end date) also

error message is "The next possible cancellation date is 07.02.2012"

jpfriends079
Active Contributor
0 Kudos

Cancellat.proc. MAHN is not a standard procedure.

Try tommorow, you will not get the error.

Regards

JP

jobi_t
Contributor
0 Kudos

If I change the date manually to 07.02.2012, getting this error : "There are no valid cancellation rules for the

requested cancellation date"

jobi_t
Contributor
0 Kudos

MAHN is defined by me, copied from standard. I tried with standard also

jobi_t
Contributor
0 Kudos

Still same

jobi_t
Contributor
0 Kudos

in Tcode ovbs, 10th Rule is missing in my system. can anybody send the date settings of rule 10. urgent

jpfriends079
Active Contributor
0 Kudos

I don't see rule 10 in OVBS.

Regards

JP

jobi_t
Contributor
0 Kudos

I got 10th.

how to check whether contract is cancelled or not.

jpfriends079
Active Contributor
0 Kudos

I don't have much idea on this.

Use Tcode VORB - Define Reference Sales Document Types for Service Contract - WV, say, MK.

Then TCode VOV8 - Sales doc type Service Contract - WV, check the Contract profile, say 0002

Now TCode VOVR - check Contract prof. 0002 and under Cancellation proced take note of Assignment cancellation procedure/cancellation rule, say, 0002 Cancel w/ 3 months notice and yr renewal.

Now, you can flow following path in SPRO:

IMG - SD - Sales - Contracts - Contract Data - Control Cancellation

Then Check the in TCode VOVN - check Assign Cancellation Rules And Cancellation Procedures

Cnacellation Procedure

Cancellation Rule

Decs

0002

0001

Cancel. up to 1 wk after contract start

0002

0003

Cancel w/ 3 months notice and yr renewal

Now refer Tcode VOVL for cancellation rule. This incidates level at which a contract may be initialted for termination

Cancellat.rule

0003 Cancel w/ 3 months notice and yr renewal

Canc.date

08 Contract Start Date + Contract Validity Period

Notice

3-

Canc.unit

3 Month

Canc.period

1

Period unit

4 Year

Therfore for your error,

The next possible cancellation date is 04.05.2013

cancellation rule (VOVL) & Contract validity period plays a vital role.

For further reference/understanding try and refer following link from SAP Help how

- [ Data on cancellation in Contract processing |http://help.sap.com/saphelp_45b/helpdata/en/b4/613275e24bd111950d0060b03c6b76/content.htm] works.

Regards