on 02-05-2012 3:14 PM
Dear All,
My client requirement is at the earlier of my project they gave some task lists with some operations having ZERO work hours .
But, Now he wants to add those and he wants some data of Task lists in that he wants Task list, Task list Description, operations and work hours and its unit..
Is there any transaction to find These values. OR Any table having all those data in it,
Please Help.
Regards,
Varma
hi
check these tables
Task list header-PLKO
Task list operations-PLPO,PLAS
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Standard report IA17 for printing task list & IA10 for multi level display of task list may be checked. However if you wants to filter based on certain parameter like where Hrs are not maintained then you have to o for Z report using table PLPO, PLKO
Shakti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.