on 02-03-2012 9:04 AM
Hi PS Guru's,
there is a WBS element i.e A , which budgeted and availability control active. I have purchased some raw material against WBS element. system check the budget and also consume the budget. now we are creting a production order and assign the wbs element A . in production order i will use the same material as RAW material which i have purchase angaist wbs elemet A. at the time of cost determination in production order system checking budget for raw material also which alredy purchase and budget has consume. we want system should check the budhet only oveheads/activity cost.
regs,
Avinash singh
Hi,
Check in the CJ31 transaction for your project in EXTRAS --> AVAILABILITY CONTROL --> ANALYSIS whic entries are consuming budget and wich entries don't consume budget.
I hope this can be useful,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check exclude cost element in the customization setting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.