Dear Team,

Our requirement for ontime delivery criteria is - for delays up to 10 days from PO delivery date to GR date 100 points, 11- 15 days delay -98 points,16-30 delay -95,31-45 delay-93,46-60 delay -90 , >60 - 1 point. how to configure this points in SPRO -points for the auto matic criteria.

Also what is the logic taken for assigning point scores for standard purchase organisation available in SAP 0001(Einkaufsorg. 0001). IF WE ARE TAKING A COPY OF THIS AND TRYING TO EDIT, SOME VALUES ARE NOT GETTING DELETED & SOME VALUES NOT GETTING SAVED.

Thanks & Regards

Nireesh

Accepted Solutions (0)

Answers (1)

Answers (1)

krishnamurty_madduri
Contributor
0 Kudos

Hi,

Vendor Evaluation (t-code ME61) has the following features:

Wighting Key: in Std. SAP two keys are given (with equal weighting & unequal weighting). Based on the criteria you have, you can either accept & follow one of these std. settings or create one for yourself in IMG.

Suppose you select equal weighting as the key to be followed: there are 4 criteria viz. Price, Quality, Delivery and Service.

Each of these criteria have sub-criteria for them. For Ex. Price has 3 sub-criteria: Price level, Price history and Price behaviour.

So, for each sub-criterion, you allocate different marks (based on your business). Again, for each sub-criterion, there is a scoring method in Std. SAP. You can't create any new scoring method of your own. You only have to follow one of the 16 scoring methods given.

Thus, the total score would come to 100 and you get vendor evaluation based on these criteria chosen.

In your case: you have descending marks (points) for delay in delivery. So, pl. make one according to those criteria & sub-criteria. Please go through the help.notes and also some links in SCN. Regards, KrishnaM