on 02-02-2012 7:08 PM
Hi All,
I have 3 changes/sub components waiting in the QA under a software component. Now i want only 1 change to move to Production.
In my current landscape i can move the whole software component to Production. is there a way that i can move move only 1 change
Our landscape has DEV-QA-PROD
keethi
Hi,
You can release the change list from QA. Tools -> export
And then you will have only one thing in the SWCV to be transported.