Hi ,

these are the budget column settings :

Key figure Overall in CAC

Version 0 Plan/Act - Version

Value Type 41 Budget

Object ind. P Project item

Debit type 1 Costs and credit-side payments

My case is the following :

Controlling Area Currency : USD

WBS object currency : EUR .

The budget on the wbs is in EUR ; unfortunately the bdg displayed into the report , has a Change rate that i dont' recognize .

E.G. Budget on the wbs 110000 EUR - bdg displayed into report : 120.153,85

If i launch the transaction cj31 i see the bdg , if i select controlling area currency , the bdg in USD >156.200,00.

This value is read from the table BPGE .

Why does the report S_ALR_87013558 don't read it also from there?

thanks and regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

in PS all the Cost reports are read from the Info Database.