cancel
Showing results for 
Search instead for 
Did you mean: 

Budget is not rolling Up

former_member195427
Active Contributor
0 Kudos

Hello Experts,

Whenever I am assigning budget against child WBS/'s and Totaling Up, The Budget is not accumulating to the Parent WBS . Also, here was a problem of -ve Available budget against those WBS. Now, even after making the budget (Available) to +ve value, the system is not behaving accordingly.

Please suggest..

Regards,

Ankur

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

As per the standard sap budget is distributed from top to bottom ,you are assign the budget in the cj30 at the lower level but that time system is check the all assigned and planned values assign the WBS, Open the cj30 and assign the budget and select all now check, the check indicator if the budget is grater then the distributed budget system allowed to do the transaction

Thanks & Regards

R.B.Rao

Answers (3)

Answers (3)

former_member195427
Active Contributor
0 Kudos

Thanks To you all. It's working now.

Regards,

Ankur

Former Member
0 Kudos

Hello

Try to run CJBN - Reconstruct Availability for Projects.

Thanks

Vamshi

Former Member
0 Kudos

Hi,

Try running the CJEN and reconstruct the project data base and then check the budget total up in CJ30.

Regards

Sreekanth