on 01-30-2012 11:14 AM
I have created one maintainace order with referesnce to WBS.The cost is appearing as Plan Apport Orders in S_ALR_87013543 with the cost in cost element.I am not able to understand what is meaning and implecation of Plan ammended orders & Plan apport Order.
Regards
Hi,
In the T.Code OPSV there is one indicator with this
if you want to include the network cost also in the wbs planning you need to check this indicator . on the bases of this indicator only the values in the report also performs S_ALR_876013543.
Regards
R.B.Rao
Edited by: Rob Burbank on Jan 30, 2012 9:36 AM
Edited by: bhavanio rao on Jan 31, 2012 3:48 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please read SAP Help on "Plan Costs from Orders for Projects"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.