7.1 Change Request ( ZMCR ). Not closing.

Former Member
0 Kudos

Hi all. We have configured solman 7.1. and copied all transaction in Z* namespace

Problem:

When i complete my ZMHF, related ZMCR are in development status and not released...

in actions tab there is 2 actions Extend scope and Check Change Request....

any advice what is wrong?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

we are using this, we faced similar issue with NC, where we got cycle status inconsistency, we solved by using question no 9 in the below blog

Thanks

Jansi

Former Member
0 Kudos

Hi and thanks for reply.

But even if i complete taks list my ZMCR not switching to status - Implemented from "being implemented".

Furthermore with standard SMHF - SMCR everything fine when SMHF status - completed, correponding SMCR switching to Implemented.

Maybe need some more costumizing to get this work.

1) copied all to Z* name space

2) define copy control for ZMCR ( to make possible of creating ZMHF )

3) activate copy control

That's all...

Regards Dan

Edited by: Daniyar Kulmanov on Feb 8, 2012 7:22 AM

Former Member
0 Kudos

Anyone use ZMCR insted of SMCR???

how you complete ZMCR???