on 01-27-2012 7:12 PM
We are trying to set up for 3rd party sales, where we will take a customer order and then send a requirement to a Vendor for fullfillment. The Vendor will ship directly to the Customer. So no inventory will be in our system, but our users are used to seeing any kind of request in the MD04 - Stock/Requirements List.
We are using Item Category TAS and Schedule Line Category CS and the process is working fine. But the users would like to see it in MD04, even if we are not physically handling the product.
I've taken a look at the MD_CHANGE_MRP_DATA Badi to try and make it show, but the records are not in the VBBE table when the sales order is entered nor are they in the VBBS table for the purchase req / order side.
Any suggestions on how to accomplish this?
The reason is due to the schedule line category (t.code VOV6) type CS. In the configuration, Req/assembly is switched off, so requirements will not be passed to MD04. The process itself is clear, the third party goods will not influence the plant stock, hence no need to pass the requirement.
To fulfill your requirement, you may turn on the field Req/assembly and test.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Debbie, it's not going to happen, by design of 3rd Party Drop ship.
It will create a Purchase Req. this has to be reviewed and converted to a P.O.
The only other automation you can affect is to have ME59 (I think that's the T-Code) run as a batch job for those types of req's, to auto convert them to P.O.'s
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.