Hi,Fiends
while creating Work center there is a CAPACITY tab in that CAPACITER HEADER DATA TAB there is Capacity utilization field
and number of individual capacities are there how to enter values in that will u plz explain me.
Your response is highly appriciated.
Regards,
Sunil
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For this question in simple words.
Workcenter Capacity = Total working hours (8 hrs) X No. of individual capacity (4) = 32 hours
Regards,
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Capacity Utlilization is to indicate how effectivily you are using this work centre. If you are using it to its full extent then the utilization is 100 else you need to populate the corresponding percentage. Number of capacities is quite straight forward; you need to maintain quatuty whether 1 or 2 or 3...
regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.