on 01-27-2012 10:51 AM
Hi Gurus,
I have a requirement where the customer wants the Material Availability Date to default to 15 days before the Delivery Date.
I have tried to maintain the pick/pack time , load time against the shipping point but it does not reflect when I create a new order.
Can someone pl. tell me what other setting needs to be done for this?
For better understanding, refer one of the SDN wiki on ATP:
- [ Available to Promise - ATP |http://wiki.sdn.sap.com/wiki/display/ERPLO/AvailabletoPromise+%28ATP%29]
Regards
JP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes it should. As any how the system determine scheduling on the bases of backward scheduling. Take into following Org structures into consideration:
- route
- shipping point
- material
- ship-to party
Generally, system will automatically determines the scheduling. If in case, the system is not able to honor the manually entered date by user then system automatically determines the earliest date on which the sales order quantity can be confirmed based on backward scheduling.
Regards
JP
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.