on 01-27-2012 7:32 AM
We have around 2500 spool request generated every day on an average.we had only 1 spool work process,last week we increased it by 1 and now 2 spool work process there in the system
But we are not getting any help from second spool work process as all spool request are handled by any one at a time and other w/p is in waiting mode.
Is there any way to make both work process work together within sap policy of "Printu2013inu2013orderu2013ofu2013generation"
I created new output device hoping that spool request created for this will go to other but no help
Regards
Shahnas.S
Any sap gurus please help me in this regard?
Can we make use of 2 spool work process at a time?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check that the "Spool Servers" in SPAD is reflecting the multiple spool processes.
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.