CJ 46 - OH Calculation issue

Former Member
0 Kudos

Hello Gurus,

I am not a PS guy but had to work on some WBS OH calculations. So here is my question.

What is the business process for running CJ46 and CJ44? We have attached a costing sheet to a WBS ELement, We posted planned values to WBS using CJ40. However, when we run CJ46, no postings are happening. So I am not sure what steps I should perform before executing CJ46 and what would happen after CJ46. I appreciate your responses.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

hemu_katta
Participant
0 Kudos

Hi. Here i am giving one example, please follow same way.After activity confirmation,in ps,the actual cost of the activity is going to settle at cost center under cost element as mentioned in kp26.Same cost elementshould be maintained in costing sheet under BASE. Than excute cj44. THAn will see oh in cji3.