How to change pricing procedure of existing purchase Order

Former Member
0 Kudos

Hi,

We have created a Purchase Order.

After PO creation, we have changed the schema group for the vendor.

Now for new Purchase Orders, new pricing procedure is determined.

We also want new pricing procedure to be determined for old Purchase Orders.

Can this be achieved?

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

It is possible to Update the Pricing procedure in Old PO. For this what you need  to do is Open PO in ME22N transaction, in the header Org. Data tab remove the Purch. Org and Company Code and press Enter Key for 3 or 4 times now enter the Purch. Org and Company Code now check in the Item Data, condition tab Analysis button new Pricing procedure is picked up. Even we can change the PO Currency in this way if it is changed in Vendor master.

Hope this will help you

Best Regards,

Pradeep Naik

Answers (4)

Answers (4)

tejyadav
Active Contributor
0 Kudos

>After PO creation, we have changed the schema group for the vendor.

Not possible.

kunal_ingale
Active Contributor
0 Kudos

update it with update button in the item pricing ,

by chooseing carryout new pricing

Former Member
0 Kudos

In condition tab, at the bottom you can see "update" with $ symbol. In ME22N, you can change the pricing procedure of PO by clicking this button

Former Member
0 Kudos

If you have not performed any subsequent transaction on that PO than yes its possible with update pricing option. Click on Update button on Conditions tab in PO and select option B.

Regards,