Material assignment & Budget checking

Former Member
0 Kudos

Dear PS experts,

Project created - Project definition, WBS elements, Network & activity. Budget assigned.

While assigning material (Item category - L, MRP 4 - Ind/Coll indicator - blank)

1. Project created status

a) If I select Procurement indicator "Reservation for network", it's showing "error in commitment check" if material value is more than the budget.

b) If I select Procurement indicator "P.Req + Reservation for WBS element", it's NOT showing any error for the same material & quantity and I am able to trigger purchase requisition from project.

2. Project released status

It's showing "error in commitment check" for both a & b.

Please help me to resolve this.

Thanks & Regards,

Murthy.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Murty ,

please check the link

Regards

R.B.rao

Answers (1)

Answers (1)

pradeep_mahamuni
Contributor
0 Kudos

Hi,

Please check if any user status is maintain for your project. May be in CRTD availability check is restricted and from REL system is checking for the availability.

Alos check in tolerence limit setting all transcation (++) setting is maintained.

regards,

Former Member
0 Kudos

Hi,

Thank you for your response.

I have not maintained any user status and Transaction group ++ is maintained.

Regards,

Murthy.