on 01-23-2012 6:14 PM
"factory calendar missing or error in factory calendar".iam getting this error while processing sales order even though i have assigned it to shipping point and plant and sales org.
Dear Gopal
If u have assigned properly in all the three areas then i would suggest you to check in T-Code SCAL --> valid from and valid to
Thanks
Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Malik, How are you? I'm sorry to trouble you,
Let me introduce, I'm Daniel, and I saw your fantastic asnwer in
the topic "How to update Factory Calendar in SRM", and might I have the same
problem. It's with the "factory calendar".
In transaction va02 when I choose a Delivery Date, and I sent it to process, as
a result in the "shipping tab" it calculated to the first item one date, and to
the rest one date different. I don't know What it happen?
I debugged the program and I saw that to the first item use to calculate the
date is the function 'APO_SCHEDULING', and to the rest item use
'SD_SCHEDULING', and until here I come.
How can I do to what the dates calculated are the same? or What would be the
problem?
I need the dates calculated are equal.
I looked at it's using two "factory calendar" which are "J4" and "C2". Is this
correct?
Thanks In Advance,
My best regards,
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.