LTP Run....

Former Member
0 Kudos

I have create a planning scenario and put here receptive inactive version on that scenario. Requirement is there on that inactive version for those material. That can i see in MD61. So when I will run LTP by MS02, then no requirement will be calculated. Also when I have checked in MS04 , there are no planned order for requirement, only showing the opening stock.

Plz give me the solution how to run LTP with planning scenario with particular material and plant.

Accepted Solutions (0)

Answers (3)

Answers (3)

anup_patil3
Active Contributor
0 Kudos

Hi,

Check if Planning Scenario has status as "Released" (Status=2).

I saw the same thred in PP forum & replied there also. Would suggest you to close this thread here & continue with PP forum.

Regards,

Anup

former_member223028
Participant
0 Kudos

step involved

1.creat a plnning scenarion MS31

2.creat a PIR MD61

3.Run MRP MS02

4.Stock requirment list MS04

5.Change stimulative plnned order if required MS12

6.Capacity evaluationCM38

7.Converting inactive version to active version:MS32

8.Now run normal MRP:MD02

Hope it help