on 01-20-2012 9:40 AM
We want that system may generate new document number against each line in CJ34 (Transfer Budget) like in Fund Management in FR14. How it is possible?
Yes, for each entry in CJI8 there is a new document number.
Check it in CJI8 transaction, it is very useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
System generates one budget document for each posting. Like each document posting may contain one line item or multiple line items. i.e. one posting = one budget document
In sap ps you can not generate new document number against each line in CJ34 (Transfer Budget).
Regards,
Sandeep