IN PROCESS INSPECTION, QM operation blocking next PP Operation

Former Member
0 Kudos

Evening dear members.

It is possible to create a QM operation which could block the next PP operation on a PP recipe/route, until the QM one is released/confirmed/finished.?

Example:

10 PP operation CLEANING

20 QM operation MICROBIOLOGY TESTS

**if results of 20 are A-OK,,,,release/open/allow**

30 PP operation 1st PP OPERATION

40 QM operation DOESNT BLOCK next operation

50 PP....... and so on

If yes, what do I have to mantain to do so?

Appreciate your feedback

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Have you tried exit CONFPP02

former_member221025
Active Contributor
0 Kudos

hi,

Create one new Control key for Inspection operations in:

QCC0>Quality Planning>Inspection Planning>Operation>Define Control Keys for Insp. Operations.

If it is for QM operation, do not forget to flag "insp char. required".

And in "Confirmation" field, Select "1" Milestone Confirmation.

now, if you assign this key (With Milestone Confirmation) for Operation 0020,0030, 0040;

System will not allow to Confirm 0030,0040 unless 0020 is not confirmed.

Check this in your Case. i hope it will solve your problem.

Regards,

Amol

Former Member
0 Kudos

Hi ou can go as per amol and set the control key. for operation 40 you can define a separate control key you can put the confirmation as 2.

Regards,

Smruti

Former Member
0 Kudos

hi

check is there any user exit available.