on 01-20-2012 4:09 AM
Evening dear members.
It is possible to create a QM operation which could block the next PP operation on a PP recipe/route, until the QM one is released/confirmed/finished.?
Example:
10 PP operation CLEANING
20 QM operation MICROBIOLOGY TESTS
**if results of 20 are A-OK,,,,release/open/allow**
30 PP operation 1st PP OPERATION
40 QM operation DOESNT BLOCK next operation
50 PP....... and so on
If yes, what do I have to mantain to do so?
Appreciate your feedback
Have you tried exit CONFPP02
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Create one new Control key for Inspection operations in:
QCC0>Quality Planning>Inspection Planning>Operation>Define Control Keys for Insp. Operations.
If it is for QM operation, do not forget to flag "insp char. required".
And in "Confirmation" field, Select "1" Milestone Confirmation.
now, if you assign this key (With Milestone Confirmation) for Operation 0020,0030, 0040;
System will not allow to Confirm 0030,0040 unless 0020 is not confirmed.
Check this in your Case. i hope it will solve your problem.
Regards,
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check is there any user exit available.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.