How to allocate cost in activity type?

Former Member
0 Kudos

Hi Gurus,

I have created a work centre and attached a Activity type in this.But while using the Activity type in PM order cost is not coming.Pls let me know how and where i need to maintain the activity price rate???

Thanks,

Baiju

Accepted Solutions (1)

Accepted Solutions (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Baiju,

You use the transaction KP26 to input (plan) an Activity price for a combination of Cost Centre/Activity type/Period

Former Member
0 Kudos

Ya fine..But i have maintained both cost Fixed and varriable ,still no cost appearing in maintenance order when putting the operation hours..Pls let me know if i am doing any mistakes.

Former Member
0 Kudos

Hi

Did you used any formula in work center, try using SAP0008 in costing tab and see the log in maintenance order for costing.

make sure that cost center/activity type should be on valid date.

Also Please check the settings.

>IMG->Plant Maintenance and Customer Service->Maintenance and Service Processing->Basic Settings--->Settings for Display of Costs.

-->Cost element used in activity type should be mapped in value category settings.

-->Also check in OIOF t.code, assign costing parameters to order types.

Regards

Seenu

Former Member
0 Kudos

Solved..superb..Thanks lot...