on 01-18-2012 7:41 PM
Hello,
i have a question regarding the use of PS-Module.
I would like to know if in your company you experienced any problem (in controlling or somewhere else) when posting to a variety of different cost objects. For example: wbs-element, sales order, internal order and network.
SAP is offering a lot of possibilities how to customize a system. That means i could run similar processes with different assignment to cost objects. I would like to know how you think about that topic and what experience you made.
Hi,
As you rightly said the SAP is providing different different cost objects to be posted.
based on the company requirement we have to choose the process.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.