Hi,
Product availability check is at component level. Based on receipt elements at component level, confirmations are done at parent material (i.e. sales order material)
Is it possible to get pegging of the receipt elements at component level against sales order of parent materials?
It is an MTS scenario.
Regards,
RS
Hi RS,
As far as I know you can not do a pegging accross different pegging area (product/location combinations). You can just do a pegging "inside" one pegging area. So you need to create e.g. a planned order for the sales order requirement and fix peg the dep. demand on component level.
best regards,
Michael