Hi,
We are on SRM7.01 with ECC 6.0 EHP 4.
This is in reference to Plan Driven Procurement.
Issue : Any Change in PR is subjected to release stratergy but on change only "without release" data transferring to SRM.
Changes like " Qty, Delivery date" etc made in PR and went for release but without considering release status changes went to SRM.
This is not the case for Fresh PR , In this case any PR subjected to release will go to SRM only after complete release.
Any Event linkage i am missing ?
Any note is availaible ?
Whats the standard behaviour ?
Advice from your side will be highly appreciated.
Regards,
Neeraj
this happens because of this..
class: CL_MMPUR_EXT_SOURCING
method: IF_EX_ME_PROCESS_REQ~POST Post
when you click save, this method is called and if you just have a quick look at it, it checks if the PR has been sent before to external sourcing .. .without checking anything else it sends again.
raise this with SAP. let the answer. you are not wrong.
so, may be in the badi can be used for time being
ME_REQ_SOURCING_CUST. clear the sourcing flags if the item is not released yet.