on 09-07-2006 7:44 PM
I wander after remote client copy from PRD to QAS do I have to change Logical system on QAS. Do I have to run some postprocessing program?
Thank you in advance
Hi Branko,
After the system copy, go to transaction SALE -> Sending and receiving Systems -> Logical systems -> Define Logical System , click New Entries and create a new logical system for your QAS; then go to SALE -> Sending and receiving Systems -> Logical systems -> Assign Client to Logical System, click on the client, click change and assign the new Logical system.
Other activities, check Jobs, RFC's, etc...
Regards
Juan
Please reward with points if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Branko,
If you cannot change the logical system in Tcode SCC4, call Tcode BDLS and change it there.
We only change T* tables to avoid a long runtime of BDLS.
Good luck,
Victor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.