Dear All,
While assigning material to activity automatically it is picking up requirement date as activity finish date but it should pick up start date
there are 3 option in that screen
Manual reqmdate
algn start date
Algn Fin date
It should automatically should pick Algn Start date
i request you to suggest any config is missing or need to change config
Thanks & Regards
Doss
Edited by: Doss27 on Jan 14, 2012 5:47 AM
In OPU6 Please remove the check Box of Latest Staging Date and try.