Requirement Picking finish date

Former Member
0 Kudos

Dear All,

While assigning material to activity automatically it is picking up requirement date as activity finish date but it should pick up start date

there are 3 option in that screen

Manual reqmdate

algn start date

Algn Fin date

It should automatically should pick Algn Start date

i request you to suggest any config is missing or need to change config

Thanks & Regards

Doss

Edited by: Doss27 on Jan 14, 2012 5:47 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

In OPU6 Please remove the check Box of Latest Staging Date and try.