Error messege BP603 while posting the parked document budget exceeded

Former Member
0 Kudos

Hi ,

We are having the budget function and its for overall release.

Budget has been relased and assigned value is less then the released budget in all conditions.

Its throwing the error messege No BP603 while posting the parked documents. Unable to understand the reason why its behaving.

Please let me know if anybody has faced such problem.

We are into ECC6, EHP 4 and the SAP note 557431 is not going to help anyways.

Regards

N.Raju

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Please follow as given below:

1. Use T.Code KO31 and enter order and deactivate the control

2. Then try to post the parked document

3. And use T.Code KO30 and enter the order to activate the control

Some times system will check budget availability which already commited for parked documents.

Hope it will work.

Chandu

Former Member
0 Kudos

hi

reconstruct the info database usign CJEN and then try with your parking the document.

also check in the S_ALR_87013558 report for the  values in the respective columns

former_member388328
Active Contributor
0 Kudos

Hi,

In OPS9, availbility control -- please check if you have given usage any value or not. If you have'nt give any value then enter some value based on your business.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

Hi,

Value can be given only if the activation type 2. That is backround activation.

This is nothing to do with the senario which i explained. Need to know how come budget avialblity control is showing error at parked document posting even though released budget is availble.

Any input on this please.

Regards

N.Raju

Former Member
0 Kudos

  Dear Narayan,

Have you tried reconstructing availability control transaction CJBN?

I think the probloem comes into picture when-

a) The invoice value is different from the PO value

b) WBS assignments have been changed in PR/PO during the course of the project.

Please let me know if it works or if there is any other solution you got.

Thanks and Regards