on 01-13-2012 9:19 AM
Dear gurus,
we are implementing ATP checks and auto rescheduling of orders.
if a production order for a material is delayed, .....do you know how this impacts the sales order that were already commited against this production order availabilty?
We are working in a make-to-stock scenario.
Thank you in advance
Best regards,
Hi,
The sales order will be rescheduled and new schedule line will be generated with new possible delivery date. So as a result the customer will not be able to be delivered on time (on requested delivery date).
Regards,
Marcin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.