Does anyone know which tcode posts values using business transaction RKP3 to WBS elements? I see secondary costs posted against a WBS element, but can't seem to find the transaction that posted it. I would like to say it is CJ40 - activity input, but I can't go into that screen in my production system, so I am assuming that it could be some other transaction.
What I am trying to get to is someone loaded some cost during data migration, and it appears as if they used an activity type with rate $1, because COSS table shows Quantity as 5000 units, where the cost is $5000 as well. This is causing some of my reports to be showing ridiculous numbers for plan hours on the project.
Any ideas?
I figured this thing out. It's basically coming from activity input for WBS (CJ40). The planning profile had to be complete.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.