Issue inMaintenace scheduling issue in Two plants with similar data set up

upinder_singh3
Explorer
0 Kudos

Hi PM Gurus

Scenario: A) We Have two maintenance Plants which have got Factory calendar assignment as per Table Data. We need to change Non Working days of factory Calenders (D1 and T2) for work centres working and do Maintenace scheduling

Issue A) Plant PL0B has got factory Calender T2 set up at work centre (WCT2) .We get Maintenace schedule Calls as per Calender set up ie No Maintenace Call (Planned call and Call date) on (Non Working Days). Here we change public holidays to working days and this throw schedule calls accordingly (thatu2019s Maintence Calls on working days only).

B) We have similar requirement to change public holidays for Calender D1 which is assigned to Work centre WCD1, then we must get maintenance calls for working days. But we find that for Plant PL0A, Maintenace Calls are generating even on non working days. Only difference between Plant PL0A and PL0B is for Work centre set up as per screen shots for Capacity data.

C) We have changed work centre data of WCD1 as per WCT2 ,but still PL0A is giving maintenance Calls on Non Working days (Not Controlled by Calender data of Work Centre )

D) Info: Scheduling indicator in Maintenace plans of both plants is TIME

Plant Factory Calender (plant Factory Calender

(Work Centre) Non Working Days Work Centre (PL0A)

PL0A U1 D1 3-Public holidays WCD1

PL0B T1 T2 Sat ,Sun and 10 Public holidays WCT2

Thanks

Upinder

Accepted Solutions (0)

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Upinder,

You should set the Scheduling indicator to "Time - factory calendar" and select a Factory Calendar if you want the Maintenance plan to be scheduled according to one of the calendars you set up.

The work centre capacity scheduling doesn't come into place here, yet - it'll allow for rescheduling once the orders are called.