Availability check- Replenishment lead time

Former Member
0 Kudos

HI Gru`s

in the part of availability check configuration i was maintain the replenishment led time 2 days( G.R processing time time 1 day+ planed delivery time 1 day) in MRP 2 View of material master. so now the issue is in the sales order system propose 3 days as replenishment lead time . so i am wondering from where the system calculates 1 day extra ..?????

regards..

kr.patchala

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member223981
Active Contributor
0 Kudos

What is the value in the "End Lead time" field in CO09? Is this corresponding to the 2 days lead time, or is it corresponding to the 3 days lead time?

If it is showing a date that corresponds to 3 days lead time, then it is likely the issue lies with the value stored in Tot. repl. lead time field in MRP 3 tab of MM (This field overwrites the other RLT settings in the MM)

Lakshmipathi
Active Contributor
0 Kudos

You also need to check the following areas:-

=> Det.pick/pack time in OVLZ

=> GR processing time in Purchasing view of material master

=> Minimum lot size in MRP1 view of material master

=> GR processing time in MRP2 view of material master

G. Lakshmipathi

jpfriends079
Active Contributor
0 Kudos

Check Tot. repl. lead time ( Total replenishment lead time (in workdays) ) in MRP3 Tab for the material master.

Regards

JP

Shiva_Ram
Active Contributor
0 Kudos

Check the route determined in the sales order and further check in t.code 0VTC, there may be time added in route definition.

Regards,

Former Member
0 Kudos

hi siva ram...

in my system there is no route determination ....

regards ...

kr.patchala

Edited by: krpatchala on Jan 10, 2012 3:11 PM

Former Member
0 Kudos

Hi,

Check your sales document type, "Lead time in days".

If its blank, put 0 to get your desired requirement.

If this field is maintained blank then, by default system will take 1 day as proposed delivery date.

Thats why in your case system is taking 3 days (2 days of replenishment lead time + 1 day of delivery lead time.)

check and revert

regards,

Mehul

Former Member
0 Kudos

hi mehul,,,

system propose the delivery date today only,,, but system proposed 3 days as replenishment lead time....

thank you...

kr.patchala

Edited by: krpatchala on Jan 10, 2012 3:09 PM