cancel
Showing results for 
Search instead for 
Did you mean: 

Change Notification Date

Former Member
0 Kudos

Hi,

I want to configure / change notification date in place of automatic taken system date at the time of creation Internal Order or the Creation of External Order.It is possible to enter notification date and time is manually. Please Suggest ?

Regards,

P. K. Singh

Accepted Solutions (0)

Answers (5)

Answers (5)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Pawan,

THis field is by default populated and visible; You can set it to changeable, if it isn't already, under field selection.

SPRO > Plant Maintenance and Customer Service > Maintenance and Service Processing > Maintenance and Service Notifications > Notification Creation > Notification Types > Set Field Selection for Notifications Field Selection for Maintenance Notifications

By default this field is populated with current system time.

To populate it with another value, you'd need a development, have a look at the user exits QQMA0025 or QQMA0014

Former Member
0 Kudos

Hi Pawan,

In notification you have a date called the Notification date, that by-default is the System date and time. This filed you can highlight if you want chage it.

If this not satisfy than tell me what exactly you want to do for changing the notification date,

Regards,

Vishal

ajitkumar
Active Contributor
0 Kudos

you can change the settings for input in Plant maintennce configuration under notiification creation > notification types > set field selection for notification > field seleciton for maintenance notification >VIQMEL-QMDAT. make it as input

Former Member
0 Kudos

Hi

You can maintain local time zone in you user profile(SU3) defualt value. system takes local time instead of sytem time zone.

Regards

Seenu

Former Member
0 Kudos

Hi Pawan,

In notification you have a date called the Notification date, that by-default is the System date.

but you have another date called the Required Start date which you can put when you are planning to start the Job.

and one more Important date and time is the Notification Release date and time, that can be the real time when your actual job is Executed.

anyway you can change the Notification date to the past date or the future date and also the Required start date.

Hope it helps you.

Regards,

Yawar Khan