on 01-10-2012 9:52 AM
In STO process after VL02N ( PGI ), stock reflecting in receiving plant (Before MB5T and MIGO ) i
where can do the changes
Thanks
Shiva
thanks for giving the answer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the STO settings to see whether its a one step process or a 2 step process.
For one step, you would have used movement type 647 or 645.
For 2- step, you would use 641 and 101.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear shiva bejugam,
If it is one step procedure then system will display the stock in destination plant though you didn't to MIGO.
If it is two step procedure then stock will be on transit mode.If you do the MIGO then only stock will be appeared in receipt plant.
You can check this in MMBE (STOCK IN TRANSITS)
Let me know if you have any further clarifications
Thanks&Regards
Raghu.k
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.