We are trying to change the setup group of a set up phase for a product in receipe using Engineering change number in ECC, there is Finish Start relationship between setup phase and produce phase.
The data is then transferred to APO . In APO when we dispaly the PDS the the setup group is not updated for produce activity.
All the operations and both the phases are valid during this period and they have FS relationship also.
Kindly suggest.
Regards
Amish
Can you check the CIF queue if there is any failed attempt to change the PDS?
You get an error when the setup group contains a setup key with the same value.
If not retransfer the PDS in overwrite mode.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amish,
Please make sure that you CIFed the new setup group and then you re-transferred the PDS.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.