Error at the time of Release and Save the WBS

0 Kudos

Dear All,

When i am going to release and save the project the below error has occurred.

Error-Release not allowed as budget is not allocated to the project. Project will be exited and data changes will not be saved!

But, i have budgeted the WBS and release the budget.

Kindly suggest.

Thanks,

Asutosh

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

There can be one more possibility, check if Deletion indicator was set for any of the WBS element of the project. WBSE with deletion indicator will not be having budgeting status if indicator set before budgeting.

Former Member
0 Kudos

Hi Asutosh..

post the snap of that error message...so that we understood very clearly....like everyone said because of user status only, you will get that issue...you can take the message id and check the same in internet.....you will get a clear idea about the issue....

Regards,

Aavula(gopi2goal)

former_member661330
Contributor
0 Kudos

Hi,

This issues looks like you have some user statuses restricting to release the project; you can see the business transaction allowed on your project

Regards

Former Member
0 Kudos

Hello ,

System status will allow you to release project. You are getting this due to user status.

Your user status say initially 1 needs to change to say 2 so that you can release your project.

This user status is defined in customization and assigned to your project profile.

Regards

Keshav

Former Member
0 Kudos

Check if the system status BUDG appears on the budgeted WBS elements. Also check if you need to set a particular user status once you have done the budgeting. Maybe, until you set this User status system wont allow you to release the project. Also check if there is any User status restricting the release of the project.