Guys,
Seek your help in fixing an issue, I am facing now.
I wanted to transfer some actual cost from one WBS to another, Hence, I tried FB01, with posting keys 40 and 50, I am able to the transfer. But, the issue I am facing here is, When I m performing the Debit posting, it gave an error message 'WBS element SEW-08901-02 is not a billing element (Message no. CJ052)'
My question here is, it is an actual cost that I am posting /transferring, not the revenue, then why the system is giving the error message like that, even, i tried to book some cost on the same WBS, but still the same message.
Is it mandatory, that for any postings /transfer for a WBS it should be a billing element? I dont think so.
Regards,
Sumanth
Hi,
As per suggested check cost elemet for which you want to post entry. If in KA03 , you find cost element catagoty as 11 then it is revenue and that's why you are getting error.
Regards
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Kindly check the cost element group in allocation structure. If the revenue cost element is mapping in the group than this error has occurred.
Thanks,
Asu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sreekanth,
I tried to check the gl/cost element, but I was not able to trace exactly whether the GL is defined as a Revenue CE. As per my understanding, the account can be defined as P&L and Balance sheet accounts.
Favor if you could let me know, where exactly I can see the same setting.
Thank you,
Regard
Sumanth
Hi Sreekanth /Keshav,
Thanks a lot for your responses.
Yes, I have checked my Cost Element in KA03 and found that the cost element category maintained for the same is 11 u2013 Revenues, hence it was giving me the message. I have user the cost element with categoty 1 and it is working with no messages.
One quick check here-
Can we use secondary cost element for actual cost transfer (from WBS to WBS) via any t-code like KB61, KB15N, KB51N etc?
Regards,
Sumanth
Did you try using KB11N for reporsting the actual costs? Try it once and let us know.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.