HI,
Actually I am in a Roll Out project. Due to some error in configuration Maintenance order cannot calculate costs. After some time we track the error and made rectification for that.
But, for orders already created before the rectification cannot have costs. My client asks me to track those costs. How will i do that? The costs for order after rectifiction is working well?
How i made the reflection for previous orders too?
Regards,
Varma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
click "Determine costs" icon in IW32 left top corner and save. it will recalculate the cost again
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.