Status of the WBS element is "Invoiced" but still WIP calculated

lavanya_latha
Participant
0 Kudos

Hello,

We have a few WBS elements whose status is "Invoiced" but when we raun KKA2, WIP is still calculated. Normally WIP is not calculated for the WBS elements whose status is "Invoiced".

Could someone please tell me what are the reasons for this. and what do I have to do to correct this.

Thanks,

Lavanya

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Lavanya Latha,

In general with PREL/REL status WIP is calculated and If project completed(TECO)or final billing(FNBL) done,Revenue calculated.

Check WBS status and if FNBL or TECO status not set,system calculating WIP correctly.

Hope this helps you..