Will anybody tell me please for maintaining QM for pre-dispatch inspection in MM02 what steps to be done.
Regards,
Sachin
DEar Sachin,
As you are mentioning MM02, i am assuming that QM view is already extended for material.
Go to QM material master in mm02, Click on "inspection Setup"
assign Inspection type "10", Flag "Active" field.
Save this change,
then Create Inspection plan for same material in QP01 with Usage 6.
Now, whenever Outbound delivery will be created, inspection lot will get created for that Outbound delivery in QA32, unless and untill you clear this insp lot, Sales person can not do PGI. (Post goods Issue)
Regards,
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sachin,
QM Proc. is not for Dispatch related settings, it is used for Procurement related settings,
So you need not to maintain any Control Key. (I am assuming that you do not purchase the same material from Vendor)
I will suggest you to Just maintain Insp type 10 and other Master data like Inspection Plan.
Get help from SD person to create Outbound delivery once you activate Inspection type 10 in Material Master.
regards,
Amol
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.