on 01-06-2012 6:33 AM
Dear Experts,
I have attached one Wbs while creting PO,And after that GR has been completed.Now i want to change that WBS element.if it is not possible Atleast i want to change description of WBS.
Example WBS Description
ABC-001-01-04-01 Electrical Works
Is it possible to change above example as below..After GRN completed
ABC-002-01-04-02 Mechanical works
or
ABC-001-01-04-01 Mechanical works
By
suma
Edited by: suma Dommaraju on Jan 6, 2012 7:34 AM
Hi,
Yes you open the project and change the description. But you cannot change the WBS number on which GR has done. Or you can just transfer the material to the correct WBSE.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't think you would be able to change anything once GR has been done. Lets wait for others to comment as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.