Issue in PO related WBS

Former Member
0 Kudos

Dear Experts,

I have attached one Wbs while creting PO,And after that GR has been completed.Now i want to change that WBS element.if it is not possible Atleast i want to change description of WBS.

Example WBS Description

ABC-001-01-04-01 Electrical Works

Is it possible to change above example as below..After GRN completed

ABC-002-01-04-02 Mechanical works

or

ABC-001-01-04-01 Mechanical works

By

suma

Edited by: suma Dommaraju on Jan 6, 2012 7:34 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Yes you open the project and change the description. But you cannot change the WBS number on which GR has done. Or you can just transfer the material to the correct WBSE.

Regards,

Harsh.

Former Member
0 Kudos

thanks for your inputs...

I rewarded the points.....

Former Member
0 Kudos

I don't think you would be able to change anything once GR has been done. Lets wait for others to comment as well.

Former Member
0 Kudos

Hai gokul,

Thanks for your quick reply

Is it possible PO has been created But GRN has not yet been done...PO release and WBs also release...Can i change WBS element at this stage...???????

By

Suma

Former Member
0 Kudos

If PO has been created manually and GR has not been done i think you can change the WBS. Haven't tried after releasing the PO. Maybe you can check this at your end.